Viet Dung Aluminum Finishing Materials Factory – Ba Thien Industrial Park, Vinh Phuc

The Viet Dung Aluminum Finishing Materials Factory project is located in Ba Thien Industrial Park, Vinh Phuc Province. The project is invested by Viet Dung Aluminum Joint Stock Company, with TEXO Consultancy and Investment JSC serving as the Construction Supervision Consultant.

Strategically located, the project benefits from excellent connectivity via road, air, and sea transportation:

  • 50 km from Hanoi Capital
  • 15 km from Vinh Yen City center
  • 6 km from the intersection of the Trans-Asia Expressway (Noi Bai – Lao Cai)
  • Adjacent to Hanoi’s Ring Road 4 and the Hanoi – Hai Phong – Kunming Economic Corridor

Type of Construction: Industrial Facility – Aluminum Finishing Materials Factory
Construction Scale:

  • Workshop area: 56,298 m²
  • Total gross floor area: 63,311 m²
  • Total land area: 100,136 m²

Construction Timeline:

  • Estimated duration: 07 months
  • Construction start: April 1, 2025
  • Handover: October 30, 2025